Creche Inspection Reports

Regulation 29 in Waterford

Premises: 6 non-compliance(s) in the latest reports we read.

An inspection records what inspectors saw on one day; services respond with corrective actions — how to read this.

10 April 2026

The Three Little Bears, Dungarvan · Regulation 29 — Premises

Provider's corrective action:
  • The registered provider stated that they are currently in the process of locating a new toilet seat and it will be installed once purchased

8 April 2026

Jigsaw Day Nursery, Waterford · Regulation 29 — Premises

Provider's corrective action:
  • We have had the electrician access the vent in the nappy changing room. He has advised us that he has ordered the replacement vent and will be fitted as soon as possible. Monitor all vents monthly to ensure they are working properly

12 February 2026

Tip Toes Community Childcare Centre, Waterford · Regulation 29 — Premises

Provider's corrective action:
  • Radiator covers have been repaired and repainted. A new finger guard has been installed on the nappy room door. All floors in the building have been professionally cleaned. Furniture and its state of repair have been added to daily checklists

28 January 2026

Kilmacthomas Montessori School, Kilmacthomas · Regulation 29 — Premises

Provider's corrective action:
  • 1. The registered providers stated that they were waiting for a dry day to treat the surface of the outdoor area. 2. The registered providers have installed de-humidifiers and placed them in each room to remove excess moisture. Once the walls have dried out, they will treat and paint them. In the meantime, the wall has been washed and the mould removed. The staff are now aware that’s the rooms require a thorough cleaning regularly. A comprehensive cleaning checklist has been developed. This was discussed at the team meeting

23 January 2026

Discovery Bay Preschool, Dunmore East · Regulation 29 — Premises

Provider's corrective action:
  • The registered provider stated that a daily site inspection form has been developed and the maintenance man has completed the tasks as follows: 1. The fire hose has been reinstated. 2. The drain has been fixed and covered. 3. The hole in the wall has been filled and plastered. 4. The floor covering will be replaced in the coming days

11 June 2024

The Children's House Montessori, Waterford City · Regulation 29 — Premises

Provider's corrective action:
  • 1 The plumber has added another connection to allow warm water to the second sink in the bathroom
  • The hole in the plaster was caused by an electrician who was installing an outdoor light. This hole is now repaired