Belmont Montessori School (IMEB Registered), Ballina · Regulation 29 — Premises

Provider's corrective action:
  • The registered provider submitted a written response to advise that the area to the side of the premises has been cleared of broken toys, equipment, wood and tyres and this area will be checked regularly to ensure it is maintained appropriately

11 March 2026

Abbey Tots, Claremorris · Regulation 29 — Premises

Provider's corrective action:
  • The service advised in writing that: Corrective and Preventive Action (d) 1. A new cistern lid was fitted securely and the toilet was checked to ensure that it is safe. 2. The broken tap in the waddler room was replaced by a tradesman. The new tap was tested after installation to ensure it is functioning correctly, provides safe water flow, and poses no risk to children or staff. To prevent recurrence of issues, a qualified plumber is to be contacted by staff immediately for any plumbing‑related maintenance concerns. All staff have been informed that plumbing issues must be reported on the same day using the maintenance log. The Person in Charge will arrange a plumber promptly

23 February 2026

Carracastle Community Childcare Service, Ballaghaderreen · Regulation 29 — Premises

Provider's corrective action:
  • The service advised in writing that: Corrective and Preventive Action (d) Area of plaster on the wall in the full day care room has been repaired. The walls will be monitored on a monthly basis and repaired if required. (e) The railings in the ability sanitary unit have been replaced and this unit is no longer ‘under repair’ and now suitable for use as a second sanitary unit to cater for the number of adults working in the service at one time. Any repairs to this sanitary unit will be done in a timely fashion to ensure that this unit remains in use for staff

28 January 2026

The Childrens House, Cross · Regulation 29 — Premises

Provider's corrective action:
  • A temporary heater has been placed in the cloakroom to increase the room temperature. A mains operated heating unit will be installed to provide an additional heat source within the preschool room. The daily room temperature of the preschool room will be monitored and recorded

1 May 2025

Tigh na Leanai Childcare Ltd, Kiltimagh · Regulation 29 — Premises

Provider's corrective action:
  • The registered provider advised in writing that: Corrective and Preventive Action (c) The ventilation system in now operational. The ventilation system is now checked on a daily basis by the staff members. (d) The two wash-hand basins have been descaled. The sinks will be descaled on a monthly basis and the process added to the cleaning schedules. (e) A nappy changing table has been reinstalled providing two nappy changing units for the numbers of children. The service will ensure in future that there are adequate nappy changing facilities for the numbers of children in the service

4 March 2025

Sasta Early Learning Centre, Charlestown · Regulation 29 — Premises

Provider's corrective action:
  • The service advised in a written response that: Corrective and Preventive Action (d) The taps have been replaced and will be checked regularly

3 October 2024

St. Tiernan's Community Playgroup, Crossmolina · Regulation 29 — Premises

Provider's corrective action:
  • (d) The registered provider advised in writing that: Corrective and Preventive Action 1. The service made immediate contact with a builder to come and assess the damage and to provide a work plan. It was agreed that repair work would be carried out during the midterm break. Hopefully this will not be a problem in the future as the tiles and ridge tiles have been replaced. 2. The registered provider made immediate contact with the plumber to come and install a boiler as arranged previously. The service will have the plumber to check the boiler on a regular basis

17 July 2024

Little Treasures Creche, Castlebar · Regulation 29 — Premises

Provider's corrective action:
  • The service advised in a written response that: Corrective and Preventive Action (e) Going forward the service will ensure to only care for 22 children in Preschool 1 playroom

30 April 2024

Breaffy Crèche & Pre-school, Castlebar · Regulation 29 — Premises

Provider's corrective action:
  • The registered provider advised in a written response that: Corrective and Preventive Action (d) The bathrooms have been painted. The painting of the other areas is in progress. The registered provider will submit evidence of the remaining painting work when completed. In future, the paintwork in the building will be checked on a regular basis

23 April 2024

Guardian Angel Montessori, Ballina · Regulation 29 — Premises

Provider's corrective action:
  • A full paint of the classroom is due over the summer. Both staff and children’s toilets have been freshly painted but due to the scale of painting the large room it will not be done until the summer when the service is closed and availability of funds. Regular maintenance of the walls and using a satin paint which is easy wipe will help make the upkeep of the walls easier for staff

1 March 2024

Barneys Playgroup, Belmullet · Regulation 29 — Premises

Provider's corrective action:
  • The registered provider advised in a written response that: Corrective and Preventive Action (d) 1. The service has ordered replacement linoleum which will be in place in the next one to two weeks. 2. New tape was placed on the area where the linoleum meets the tiles. The registered provider has put up a notice to remind staff to review these areas to ensure the tape is in good order

30 May 2022

Tir Na NÓg Preschool, Westport · Regulation 29 — Premises

Regulation 29 in other counties