Fire safety measures: 11 non-compliance(s) in the latest reports we read.

An inspection records what inspectors saw on one day; services respond with corrective actions — how to read this.

15 June 2026

The Ferns Preschool, Portarlington · Regulation 26 — Fire safety measures

Provider's corrective action:
  • Fire alarm system maintenance check conducted on 08 July 2026. Agreement that an electrician will visit every June to check/update and certify equipment

19 March 2026

Darling Buds Montessori & Daycare, Portlaoise · Regulation 26 — Fire safety measures

Provider's corrective action:
  • (1) (a) Fire drills were completed on 24 March, 27 April and 15 May 2026 following the inspection. Monthly fire drills will be completed in line with regulations and completed monthly

9 March 2026

The Maples Creche, Portlaoise · Regulation 26 — Fire safety measures

Provider's corrective action:
  • The fire extinguishers were service the day after the inspection, 10 March 2026

21 January 2026

Classy Kidz, Ballylinan · Regulation 26 — Fire safety measures

Provider's corrective action:
  • (1) (a) A fire drill was conducted on the 26 January 2026. Monthly fire drills will be put into the diary and carried out regularly. (b) The firefighting equipment was serviced on 23 January 2026

11 December 2025

Claire's Montessori, Mountmellick · Regulation 26 — Fire safety measures

Provider's corrective action:
  • (1) (a) A fire drill was carried out in the service immediately post inspection. The registered provider allocated fire drill monitoring to staff members monthly tasks. (b) Maintenance of the smoke detection alarms was completed on 14 January 2026. The registered provider plans to enter into an annual contract with the fire safety system company for annual checks. A staff member has been allocated the task of fire detection equipment monitoring

14 October 2025

Iosa Linn, Portlaoise · Regulation 26 — Fire safety measures

Provider's corrective action:
  • (1) (b) The company that maintains the fire equipment had been contacted within the week timeframe that they were due out (September 2025). Maintenance checks were conducted on the fire equipment in October 2025. The company that service the equipment usually do so automatically every year, in future the service will notify them at least 4 weeks in advance of the certificate being out of date

3 October 2025

O’Moore Place Childcare, Portlaoise · Regulation 26 — Fire safety measures

Provider's corrective action:
  • Maintenance records for the smoke detection system were forwarded onto the inspectorate

16 September 2025

Little Scholars Montessori School, Portlaoise · Regulation 26 — Fire safety measures

Provider's corrective action:
  • Maintenance of the smoke alarm system was conducted on 30 September 2025. Fire safety and maintenance checks will be conducted at the start of each academic year as part of the building’s yearly maintenance

16 June 2025

Little Learners Pre-School, Graiguecullen · Regulation 26 — Fire safety measures

Provider's corrective action:
  • A fire drill was conducted in the service on 17 June 2025. Staff have been reminded to ensure fire drills are conducted monthly

21 May 2025

Early years service TU2015LS006, Portlaoise · Regulation 26 — Fire safety measures

Provider's corrective action:
  • Maintenance record obtained for fire extinguishers and fire blankets dated 31/03/2025. Smoke alarms were tested on 06/06/25

2 December 2024

Superkids Childcare Centre, Portlaoise · Regulation 26 — Fire safety measures

Provider's corrective action:
  • A fire drill was carried out. Fire drill dates have been scheduled for the coming year. (Fire drill record included) Summary Comment In respect of the corrective action taken documentary evidence was submitted to the office of the Early Years Inspectorate, reviewed by the Early Years Inspector and deemed to meet the regulatory requirement